dc.description.abstractTime and cost overruns in highway construction are usual in Colombia. Contractors regularly fail in cost estimation and construction scheduling. An analysis of important factors on time and cost overruns in highway construction in southwest Colombia is presented in this paper. Forty highway construction projects were reviewed. Data from construction documents were collected to prepare a data base for probabilistic analysis. Data collected include scheduled construction time and cost, actual construction time and cost, and unexpected events which could have affected the construction process. Data were used in a probabilistic cost and schedule risk analysis to identify critical factors in construction time and cost overruns in the region. It was found that the activities that most affect the time and cost overruns are the construction of the granular base and the asphalt layer. The most common causes of construction overruns were found to be poor cost and duration estimates, rain, and materials supply problems.
dc.format.mimetypeapplication/pdf
dc.language.isospa
dc.publisherUniversidad Nacional de Colombia (Sede Medellín). Facultad de Minas.
dc.relationhttps://revistas.unal.edu.co/index.php/dyna/article/view/47453
dc.relation.ispartofUniversidad Nacional de Colombia Revistas electrónicas UN Dyna
dc.relation.ispartofDyna
dc.rightsDerechos reservados - Universidad Nacional de Colombia
dc.rights.urihttp://creativecommons.org/licenses/by-nc/4.0/
dc.subject.ddc62 Ingeniería y operaciones afines / Engineering
dc.titleEffects of uncertainty on scheduling of highway construction projects
dc.typeArtículo de revista
dc.type.driverinfo:eu-repo/semantics/article
dc.type.versioninfo:eu-repo/semantics/publishedVersion
dc.identifier.eprintshttp://bdigital.unal.edu.co/58989/
dc.relation.referencesGómez, Hernán Darío and Orobio, Armando (2015) Effects of uncertainty on scheduling of highway construction projects. DYNA, 82 (193). pp. 155-164. ISSN 2346-2183
dc.rights.accessrightsinfo:eu-repo/semantics/openAccess
dc.subject.proposalHighway Infrastructure
dc.subject.proposalconstruction scheduling
dc.subject.proposaltime overrun
dc.subject.proposalcost overrun
dc.type.coarhttp://purl.org/coar/resource_type/c_6501
dc.type.coarversionhttp://purl.org/coar/version/c_970fb48d4fbd8a85
dc.type.contentText
dc.type.redcolhttp://purl.org/redcol/resource_type/ART
oaire.accessrightshttp://purl.org/coar/access_right/c_abf2


Files in this item

Thumbnail

This item appears in the following Collection(s)

Show simple item record

Atribución-NoComercial 4.0 InternacionalThis work is licensed under a Creative Commons Reconocimiento-NoComercial 4.0.This document has been deposited by the author (s) under the following certificate of deposit